Kitchen Remodeling Timeline

What happens week by week, which stages run in parallel, and the items that most often set the overall schedule.

Call now FOR FREE QUOTE and for service availability. Please have your 5-digit ZIP code ready.

Homeowners reviewing stone samples and cabinet finishes with a kitchen designer

The sequence, stage by stage

StageWhat happensNotes
DiscoveryGoals, scope and budget range discussed; kitchen measured and assessed.Fast, but it sets everything that follows.
DesignLayout resolved, elevations drawn, cabinetry specified.Homeowner decision speed is the main variable.
SelectionsCabinets, stone, tile, flooring, fixtures, appliances chosen.Runs alongside design; delays here delay ordering.
ApprovalsPermit applications and, where applicable, association submittals.Review times are outside anyone's control.
OrderingCabinetry and long-lead items released.Cabinet lead time usually sets the construction start.
DemolitionExisting kitchen removed; conditions confirmed.Surprises, if any, appear here.
Rough tradesPlumbing, electrical, framing, ventilation.Inspections required before closing walls.
Drywall and paintWalls closed, finished and primed.Drying time is real and cannot be compressed much.
Cabinet installationBoxes set, leveled and secured.The project suddenly looks finished. It is not.
Templating and stoneCounters templated, fabricated and installed.Fabrication time falls between the two site visits.
Tile and flooringBacksplash and floor completed.Backsplash usually follows countertop installation.
Finish and punchFixtures, appliances, hardware, adjustments, cleanup.Small items, high visibility.

What most often extends a schedule

  • Selections made late, which delays ordering rather than construction
  • Cabinetry lead times, particularly for custom millwork
  • Permit and inspection scheduling
  • Condominium approval processes and restricted work hours
  • Conditions found at demolition in older homes
  • Scope added mid-project after materials were already ordered
  • Backordered appliances that affect cabinet openings
  • Stone fabrication scheduling during busy season

Living through it

Plan a temporary kitchen before demolition: refrigerator, microwave, kettle and a sink you can reach. Most households set this up in a garage, laundry room or dining area and find it perfectly workable.

Expect dust despite containment, expect noise during rough trades, and expect the last ten percent to take longer than it looks like it should. The punch list is where quality is actually delivered.

Answers

Questions homeowners ask

How long is a kitchen remodel from first call to finished?
Design and selections take weeks, cabinetry lead time follows, and construction runs from a few weeks for a straightforward renovation to considerably longer for layout changes. The planning phase is usually longer than people expect and the construction phase is roughly what they expect.
Can construction start before all selections are made?
Demolition can, but it is a poor idea. Late selections stall the sequence at the worst point, with the kitchen already unusable.
Will we be without a kitchen the whole time?
From demolition through appliance installation, yes. A temporary kitchen elsewhere in the home covers it.
What is the single biggest schedule risk?
Cabinetry lead time, followed by decision delays. Both are largely controllable by ordering early and finalizing selections before demolition.

Request a Free Kitchen Remodeling Quote

Tell us about your kitchen and we will follow up to discuss scope, selections and next steps. Email is optional — a phone number and ZIP code are enough to get started.

Prefer to talk it through? Call 561-782-4361. Call now FOR FREE QUOTE and for service availability. Please have your 5-digit ZIP code ready.

Ready to plan your kitchen remodel?

Share your kitchen size, scope and timeline and we will follow up with a project-specific quote.

Call now FOR FREE QUOTE and for service availability. Please have your 5-digit ZIP code ready.

Call 561-782-4361Free Quote